070-178 無料問題集「Microsoft Project 2010, Managing Projects」

You have a task named Tasks that has a duration of four days and a finish-to-finish relationship with a task named Task4. You need to reconfigure Tasks to be a milestone. You also need to retain the original duration and resource assignments. You select Tasks. What should you do next?

A section of your project contains only a summary task along with four subtasks and a milestone. You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering. You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering. What should you do?

You have a list of tasks in Microsoft Excel 2010. You need to create a Microsoft Project 2010 schedule that maintains the order of the tasks. Which two actions could you perform? (Each correct answer presents a complete solution. Choose two.)

正解:A、B 解答を投票する
You receive approval for a project plan that is yet to start. You need to ensure that all project tasks start no earlier than September 13, 2010. Which project level field should you set?

The milestones in your project schedule represent the end of phases. You need to change the background color of the cells of the milestones to blue. What should you do on the Format tab?

You are reviewing the task details of your project. You receive the following warning message:
"This task has resources assigned which are over-allocated." You need to be able to identify a possible resolution for the over-allocated resources.
What should you do?

You need to create a project plan that accommodates the corporate holiday calendar. What should you do?