1Z1-1075 無料問題集「Oracle Manufacturing and Maintenance Cloud 2019 Implementation Essentials」
A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is
assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given
work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours.
The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given
work order at noon.
What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?
正解:B
解答を投票する
Work order costs are computed based on material and resource transactions reported and the cost method of
the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring
proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of
the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
the product. In a manufacturing plant, the production operator has completed a work order WO-001 ensuring
proper materials and resource transactions. The materials are costed and resources are defined with rates.
A cost accountant has created cost accounting distributions. Upon reviewing the accounting distributions of
the work order WO-001, resources charged to the work order are missing.
Identify the Concurrent Request that needs to be submitted to transfer resource charges to cost accounting.
正解:D