1z0-1047-22 無料問題集「Oracle Absence Management Cloud 2022 Implementation Professional」
A worker is scheduled to work from Monday to Friday. As an HR administrator, you receive a call from the worker on Friday evening 16-Jun-2017, that they are on vacation from 17-Jun-2017 (Saturday) and will be back at work on 26-Jun-2017 (Monday). The absence type for vacation has no duration formula or plans attached and the duration is measured in Days. There is a calendar exception on 23-Jun-2017 (Friday).
What should be the start date, end date, and the duration of this absence record if the "Schedule nonworking days" is set to "Not enabled"?
What should be the start date, end date, and the duration of this absence record if the "Schedule nonworking days" is set to "Not enabled"?
正解:E
解答を投票する
After running the calculate accrual process, you notice that 100 employees' balances have not been updated despite the process running to a successful status. Your customer has requested that the process should fail if any employee is in error.
What absence batch parameter should you decrease to achieve this requirement?
What absence batch parameter should you decrease to achieve this requirement?
正解:A、B、C
解答を投票する
A customer created a public holiday on the 25-Dec-2018 (Tuesday) and assigned it to a geography to which an employee belongs to. However, the employees do not have a work schedule assigned. The employee records an absence from 24-Dec-2018 (Monday) to 26-Dec-2018 (Wednesday) using an absence type that measures duration in Days.
What will be the duration of the absence recorded?
What will be the duration of the absence recorded?
正解:E
解答を投票する
A customer requires their administrator to enter the paternity leave for their employees. Paternity leave can only be entered if an employee hasn't taken an absence called special absence in the previous 30 days of the paternity leave start date. The customer requires also that this paternity leave absence is only available for the employees who have one year of seniority in the company. Employees should notify of the absence at least 30 days in advance of the start date of the absence; otherwise, the absence is not considered timely.
Which configuration should you use to implement these requirements?
Which configuration should you use to implement these requirements?
正解:C
解答を投票する