A manufacturing plant has two shifts of eight hours each for the work center WCI: day shift and night shift. You associate four units each of the resources R1, R2, R3, and R4 to WCI. The customer wants to assign ail units of R2 available for day and night shift.
What is the correct sequence of steps to achieve this?
What is the correct sequence of steps to achieve this?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A Plant Manager bought several machines for their ABC manufacturing plant. The plant is set up with a separate cost element set, ABC, in Manufacturing Cloud.
How must the Plant Manager configure these machines so that they are costed to the work order for which operations are performed on them?
How must the Plant Manager configure these machines so that they are costed to the work order for which operations are performed on them?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A Production Operator is executing a work order at your plant. After completing move transactions, they notice that they have performed some incorrect move operations, including incorrect scrap and reject transactions.
They must perform a reverse transaction to correct the errors. The operations are not count point-enabled and not auto-charged.
Which four transactions are required to correct this situation?
They must perform a reverse transaction to correct the errors. The operations are not count point-enabled and not auto-charged.
Which four transactions are required to correct this situation?
正解:B、C、D、F
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)