1z1-902 無料問題集「Oracle Exadata Database Machine X8M Implementation Essentials」
A new Exadata Quarter Rack with 2 Database Servers and 3 HC Storage Servers and 3-phase 15kVA PDUs is being installed in a Data Center. However, the Data Center is only providing enough power for a single cable from each PDU.
Which statement is correct?
Which statement is correct?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You are updating your Exadata X9M-2 Elastic Database Machine with 6 database servers and 12 High Capacity Storage Servers. You will be using patchmgr to apply updates across the entire machine while still maintaining database availability.
Assuming you are driving patchmgr from an external server, which statement is true about the execution phase?
Assuming you are driving patchmgr from an external server, which statement is true about the execution phase?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Examine these commands:
1. Execute "crscti stop cluster -all" as the grid user from one database server.
2. Execute "crscti stop cluster -all" as root from one database server.
3. Power off all network switches.
4. Execute "crscti stop cluster" as root from one database server.
5. Execute "crscti stop cluster" as the grid user from one database server.
6. Power off the rack using the power switches on the PDUs.
7. Execute "shutdown -h now" on all database servers.
8. Execute "shutdown -h now" on all Exadata storage servers.
Which is the correct order or the required commands to completely power off an Exadata Database Machine in an orderly fashion?
1. Execute "crscti stop cluster -all" as the grid user from one database server.
2. Execute "crscti stop cluster -all" as root from one database server.
3. Power off all network switches.
4. Execute "crscti stop cluster" as root from one database server.
5. Execute "crscti stop cluster" as the grid user from one database server.
6. Power off the rack using the power switches on the PDUs.
7. Execute "shutdown -h now" on all database servers.
8. Execute "shutdown -h now" on all Exadata storage servers.
Which is the correct order or the required commands to completely power off an Exadata Database Machine in an orderly fashion?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)