You plan to monitor the status of the motherboard, memory, power, fans, and network cards on the database nodes in your Exadata Database Machine using Enterprise Manager.
Where must you set the thresholds for these hardware components and why, to assure that sensor readings, faults, and any related alerts, are visible in Enterprise Manager?
Where must you set the thresholds for these hardware components and why, to assure that sensor readings, faults, and any related alerts, are visible in Enterprise Manager?
正解:C
解答を投票する
You are providing oversight for the delivery of a new Exadata Database Machine.
1. Stabilize the Exadata Rack.
2. Unpack Oracle Exadata Rack.
3. Review the safety guidelines.
4. Let the Exadata acclimatize for 24 hours.
5. Power on Exadata PDU A.
6. Place Exadata in its allocated space.
7. Power on Exadata PDU B.
What is the correct order of these steps?
1. Stabilize the Exadata Rack.
2. Unpack Oracle Exadata Rack.
3. Review the safety guidelines.
4. Let the Exadata acclimatize for 24 hours.
5. Power on Exadata PDU A.
6. Place Exadata in its allocated space.
7. Power on Exadata PDU B.
What is the correct order of these steps?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You have configured a multirack Database Machine with two X9M-8 full racks all in a single cluster and storage grid comprising a total of 4 X9M-8 Database servers and 28 X9M-8 Storage servers.
Which two options are true regarding the servers on which Enterprise Manager agents must be deployed in order to monitor all components of this multirack configuration?
Which two options are true regarding the servers on which Enterprise Manager agents must be deployed in order to monitor all components of this multirack configuration?
正解:D、G
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)