AACE-PSP 無料問題集「AACE International Planning & Scheduling Professional (PSP)」

How could the structural steel drawing delay have been prevented?

SUBCO is a potential concrete bridge contractor based in a metropolitan area 300 miles away from your project. They have offered to supply manpower and equipment t BILCO at a per diem rate of $3,000 above their direct labor and equipment rates. In doing a cost benefit analysis, which of the following is NOT a consideration?

Constraints control events or activities that __________________.

Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

These are the activities on the critical path:

A driving relationship is _____________________.

Determine the correct formula and date for the late start for the Activity 11001:

Total float is defined as the amount of time an activity can be delayed without impacting

Project schedules help control all of the following EXCEPT for_____________________.

In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?