Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A system administrator has created a Marketing Request Queue that routes to the marketing team. This team needs to manage various incoming requests from the organization through emails, instant messaging, and conversations. Team members receive request notifications in their emails but are still having difficulties monitoring and prioritizing incoming requests.
Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?
Which reports would be helpful to have on a dashboard for the marketing team to manage incoming work requests?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)