You are managing a project that is approaching its final phase and is soon to be handed over to the operations team. One of the critical aspects of this transition is the effective engagement of stakeholders.
正解:
See the Explanation for both solutions in detail:
Explanation:
Describe three key strategies you would use to engage stakeholders in agreeing to a transition plan (3 marks):
* Regular communication: Conduct consistent updates to build trust and clarify expectations.
* Collaborative workshops: Involve stakeholders in planning workshops to foster ownership.
* Tailored stakeholder engagement: Address individual needs with customized communication.
Explain two ways you would ensure the transfer of risks is understood and accepted by all stakeholders involved in the transition (2 marks):
* Documented risk register: Provide a clear and shared record of risks with mitigation strategies.
* Risk workshops: Conduct sessions to explain residual risks and their management post-transition.
Detailed Explanation:
You are overseeing a construction project for a new retail center. Midway through the project, the design team proposes a significant change to the building's layout, which they argue will improve overall functionality and therefore present better value for money. However, this change would require demolishing and rebuilding a section of the structure.
Given the proposed changes, outline five actions you would take to evaluate the change request to provide an appropriate recommendation.
正解:
See the Explanation for both solutions in detail:
Explanation:
* Conduct a cost-benefit analysis.
* Review the project scope and objectives.
* Assess risks associated with the change.
* Engage stakeholders for input and alignment.
* Develop a recommendation document.
Detailed Explanation:
Quality control activities help to prevent problems being passed on to customers. State two quality control checks that may be carried out during a project:
正解:
See the Explanation for both solutions in detail:
Explanation:
* Testing deliverables against specifications.
* Conducting milestone inspections to identify defects.
Detailed Explanation:
* Testing Deliverables:Ensures alignment with client expectations and standards.
* Inspections:Prevents issues from escalating by catching them early in the lifecycle.
Which of the following are not typical responses to risks?
* Complete root cause analysis to understand why the situation has occurred.
* Reduce the probability of the threat occurring or the impact on the project.
* Change objectives or practices to change the cause of the threat so it can no longer occur.
* There are no acceptable or viable approaches to take to avoid or reduce, so the threat and any residual risk must be managed.
* Prepare a risk management plan to document the risk and give it to your sponsor.
* Pass the responsibility for bearing the impact of the threat from one party to another.

解説: (JPNTest メンバーにのみ表示されます)