You are the Scrum Master of a project to construct an IT Tech Park. This project requires adhering to stringent quality standards at every stage of development. A Scrum Core Team is formed for this project in which the Scrum Master is supposed to facilitate a "team first" mentality when it comes to quality. You must ensure all of the following to maintain quality in Scrum, EXCEPT:
正解:C
解答を投票する
Suppose you are a Scrum Master on a project to design a metro rail system for a city. It has been brought to your attention that the Product Owner wants to change the Acceptance Criteria for one of the User Stories committed to for the current Sprint because the customer has changed a critical business requirement. Which one of the following statements presents the best solution for such a situation?
正解:B
解答を投票する
A company is transitioning to Scrum. The Scrum Master tells the management team that the role of traditional management does not exist in an Agile environment. The management team asks what the managers should do once the company has transitioned to Scrum. They feel insecure about letting all control go and wish to supervise the Scrum teams closely.
What should the Scrum Master teach the Scrum teams and the managers about Scrum?
What should the Scrum Master teach the Scrum teams and the managers about Scrum?
正解:B
解答を投票する
A company that builds propellers for ships has incurred heavy losses while implementing the product at the end of the project. This is because a large number of customer requirements which changed during the project were not incorporated into the deliverables. The company could have avoided this situation if it had applied the Scrum Methodology, as it would have ensured that any change requested by the customer was included as part of the project, and that the team produced deliverables that were better suited to the final business environment. Which Scrum aspect is being emphasized here?
正解:D
解答を投票する
The Scrum Master can help the Product Owner update business justification in the Project Vision statement and ensure continuous value justification for projects by facilitating which of the following processes?
A) Conduct Daily Standup
B) Groom Prioritized Product Backlog
C) Retrospect Project
D) Sprint Deliverables
A) Conduct Daily Standup
B) Groom Prioritized Product Backlog
C) Retrospect Project
D) Sprint Deliverables
正解:D
解答を投票する
A Scrum team uses a Scrum board. They have recently introduced work-in-progress limits (WiP-limits) and blocker tickets to improve flow. The blocker tickets show on which tickets the Developers cannot currently work The Product Owner walks past the Scrum board and sees a blocker ticket in the 'doing' column with a WiP-limit of 2 He suggests that the ticket affected is moved back to the waiting to be done' column so that another ticket can be worked on in the meantime How should the Scrum Master respond to this suggestion?
正解:C
解答を投票する
A company changes to Scrum. This gets some people out of their comfort zone and creates resistance. One way of finding out how to deal with this resistance is looking at the individuals resisting. Suppose that you categorize all individuals into Conservers, Pragmatists and Originators.
What are the best activities to help Pragmatists transition to Scrum?
What are the best activities to help Pragmatists transition to Scrum?
正解:B
解答を投票する