AgilePM-Practitioner 無料問題集「APMG-International Agile Project Management (AgilePM) Practitioner」

What action should the Project Manager take during the Close-Out of Timebox C?

Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Delivery Plan?

正解:D、E 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Which 2 actions should the Workshop Facilitator take when preparing for the workshop?

正解:B、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
How should the Project Manager assist the electricians to deliver the wiring?

Answer the following questions about actions to be taken by different roles.
The Business Sponsor has decided that the new coffee shop insurance product website pages will include the financial transaction functionality to support the end-to-end sales process. The Business Sponsor views this as a valuable sales tool, enabling customers to pay for insurance policies online. If successful, this new financial transaction functionality is to be made available across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work required to deliver the required solution including the new Must Have requirement. The areas to be discussed include specialist skills required and possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in each question.
Which 2 actions should the Business Sponsor take to implement the new Must Have requirement?

正解:A、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?

Which 2 individuals would be suitable for the role of Workshop Facilitator?

正解:A、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Which 2 actions should the Project Manager take to implement the new Must Have requirement?

正解:B、E 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)