A customer moves in to a premise and requests electricity service starting on June 7. According to the schedule records, the scheduled meter reading date is June 29, the scheduled billing date is July 1, and the allocation date for billing is June 30.
Given that batch billing is executed every night with all portions included, what is the first day the customer's contract could be billed?
Given that batch billing is executed every night with all portions included, what is the first day the customer's contract could be billed?
正解:C