(A)Daily stand-up meetings
(B)Continuous integration
(C)Retrospective meetings
(D)Pair programming
(A)To establish the team,s working practices
(B)To gather and prioritize requirements
(C)To plan and prepare for the first sprint
(D)To create a high-level design for the product
(A)The criteria that must be met in order for a project to be considered complete
(B)The criteria that must be met in order for a sprint to be considered successful
(C)The criteria that must be met in order for a product increment to be considered complete and ready for release
(D)The criteria that must be met in order for a user story to be considered complete
(A)By the stakeholders
(B)By the scrum master
(C)By the product owner
(D)By the development team
(A)Iteration
(B)Sprint
(C)Release
(D)Cycle
(A)Top-down estimation
(B)T-shirt sizing
(C)Bottom-up estimation
(D)Planning poker
(A)Following a plan over responding to change
(B)Responding to change over following a plan
(C)Working software over comprehensive documentation
(D)Individuals and interactions over processes and tools