Supplier X provides software critical to production at EFG Corporation. Supplier X informs EFG that the software version it currently uses will no longer be supported and recommends an upgrade to a newer version.
However, EFG is very pleased with the performance of the current version, and the costs for upgrading are prohibitive at this time. EFG wants to find incentives for Supplier X to continue supporting EFG's needs. In this situation, which of the following would be the BEST course of action for EFG to take?
However, EFG is very pleased with the performance of the current version, and the costs for upgrading are prohibitive at this time. EFG wants to find incentives for Supplier X to continue supporting EFG's needs. In this situation, which of the following would be the BEST course of action for EFG to take?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Due to growth, a private school system finds that its costs for support, including maintenance and janitorial services, have increased dramatically. Though supply management generally does a good job in managing service contracts, there Is no strategic plan or systematic method for reviewing costs on a long-term basis.
The school's board has made the development of a strategic plan the supply manager's priority assignment for the next school year. Given this situation, which of the following should be the supply manager's FIRST step in developing this plan?
The school's board has made the development of a strategic plan the supply manager's priority assignment for the next school year. Given this situation, which of the following should be the supply manager's FIRST step in developing this plan?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A manufacturing firm creates a steering committee to review a proposal to manufacture a new product. The product is regarded by the firm's sales team as a customer requirement based on "voice of the customer" input.
In the past, this product was seen as a high-risk noncore item, but the situation has now changed enough for the firm to warrant consideration. The firm's supply manager is tasked with developing a sourcing plan for the steering committee. In this situation, which of the following is the NEXT course of action the supply manager should take?
In the past, this product was seen as a high-risk noncore item, but the situation has now changed enough for the firm to warrant consideration. The firm's supply manager is tasked with developing a sourcing plan for the steering committee. In this situation, which of the following is the NEXT course of action the supply manager should take?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An operations manager wants to replace the existing fleet of aging vehicles owned by the company. The operations manager presents the supply manager with a list denoting the quantity, makes and models currently in operation:
Quantity
Brand A - 4X4 SUVs15
Brand B - Midsize Cars5
Brand C - Compact Cars45
Which of the following is the BEST course of action for the supply manager to take?
Quantity
Brand A - 4X4 SUVs15
Brand B - Midsize Cars5
Brand C - Compact Cars45
Which of the following is the BEST course of action for the supply manager to take?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
XI Corporation awards a contract for the building of a prototype critical to its introduction of a new product line. To protect itself against delays and unsatisfactory quality, which of the following is MOST appropriate for Xi's supply manager to require from the contractor?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A supply manager is planning a major sourcing event and wants to increase competition, especially by small and minority-owned businesses. The supply manager strives to maintain fairness with all suppliers. Which of the following is the BEST way to encourage diverse suppliers to participate?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A supply manager for DEF Inc. meets with the firm's operations team to discuss the requirements for a new piece of equipment. The team establishes the specifications, and the supply manager begins contacting suppliers. The supply manager finds that almost everything specified is outside the normal features of the equipment and will require custom modifications. These modifications will raise the cost to 2.5 times the amount budgeted. In this situation, which of the following should the supply manager do?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)