A company decides to adopt a total quality system and has started the process by developing quality policies.
Rank in order, from first to last, the rest of the steps that need to be performed to implement this system.
1.Audit the system
2.Determine system requirements
3.Develop a measurement system
4.Perform continuous improvement activities
H Calculator
Rank in order, from first to last, the rest of the steps that need to be performed to implement this system.
1.Audit the system
2.Determine system requirements
3.Develop a measurement system
4.Perform continuous improvement activities
H Calculator
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The table below shows the results of inspecting 3,752 items. On the basis of this information, a Pareto chart would show what cumulative percent of nonconformities by the end of the third operation?
Order of OperationNumber of Nonconforming ItemsPercent of Nonconforming ItemsPercent of Nonconformities
1-3729.9%55.0%
2nd1564.2%23.3%
3 rd782.1%11.7%
4*501.3%7.2%
5th200.5%2.8%
Calculator
Order of OperationNumber of Nonconforming ItemsPercent of Nonconforming ItemsPercent of Nonconformities
1-3729.9%55.0%
2nd1564.2%23.3%
3 rd782.1%11.7%
4*501.3%7.2%
5th200.5%2.8%
Calculator
正解:C