You have been asked to implement formal reviews at your company. From the list below, what are the correct characteristics of a formal review?
a. Entry and exit criteria have been defined.
b. Checklists created to be used by all reviewers.
c. Consistency with current project plan is checked.
d. Metrics on effectiveness will be gathered.
e. The review will be moderated by a lead auditor.
a. Entry and exit criteria have been defined.
b. Checklists created to be used by all reviewers.
c. Consistency with current project plan is checked.
d. Metrics on effectiveness will be gathered.
e. The review will be moderated by a lead auditor.
正解:D
解答を投票する
'Safe as Houses' is a company that specialises in home security software, including alarm systems, surveillance cameras and other forms of deterrence.
It is currently developing the software for a device which simulates an active television, producing sound and light images that suggest someone is home watching the television. 'Safe as Houses' recently won a lucrative contract to supply the software to Smart Alarms', who will be manufacturing the hardware devices Sound will be created using actual television and film archives, licensed through a third-party supplier, 'Silver Sound Ltd'. A user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a programme of work, consisting of three projects. Project 1 will develop the software for the light images. Project 2 will develop the sound system and Project 3 will integrate the two using hardware prototypes supplied from 'Smart Alarms'. The programme will conclude with 'Smart Alarms' performing User Acceptance testing in usability labs.
The 'Safe as Houses' test team has experience in testing alarm and surveillance systems but lacks experience in testing light imagery software. The organisational test policy includes the following objectives:
1 Exploratory testing should be used to augment more formal, structured testing within constraints of time and budget
2. Test automation tools should be purchased and employed to maximise the breadth and efficiency of regression testing The Programme risk register currently includes the following risks:
RISK1 Working prototypes will be delivered late to the integration test environments RISK 2 A delay in signing the contract with 'Silver Sound Ltd' will impact the programme schedule RISK 3 Inexperience in testing light imagery software will cause major defects to be missed RISK 4 The user interface software for the sound systems will be delivered late into testing Refer to SCENARIO 2 - The IT Director for 'Safe as Houses' is recruiting a Programme Test Manager and has been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (5 being highest. 1 lowest) for each candidate:

Consider which of these skills are key for a Programme Test manager in this scenario. Based on these, which candidate would be the most suitable?
SELECT ONE OPTION
It is currently developing the software for a device which simulates an active television, producing sound and light images that suggest someone is home watching the television. 'Safe as Houses' recently won a lucrative contract to supply the software to Smart Alarms', who will be manufacturing the hardware devices Sound will be created using actual television and film archives, licensed through a third-party supplier, 'Silver Sound Ltd'. A user interface will be developed in house to allow the customer to choose sound tracks.
The software will be delivered as a programme of work, consisting of three projects. Project 1 will develop the software for the light images. Project 2 will develop the sound system and Project 3 will integrate the two using hardware prototypes supplied from 'Smart Alarms'. The programme will conclude with 'Smart Alarms' performing User Acceptance testing in usability labs.
The 'Safe as Houses' test team has experience in testing alarm and surveillance systems but lacks experience in testing light imagery software. The organisational test policy includes the following objectives:
1 Exploratory testing should be used to augment more formal, structured testing within constraints of time and budget
2. Test automation tools should be purchased and employed to maximise the breadth and efficiency of regression testing The Programme risk register currently includes the following risks:
RISK1 Working prototypes will be delivered late to the integration test environments RISK 2 A delay in signing the contract with 'Silver Sound Ltd' will impact the programme schedule RISK 3 Inexperience in testing light imagery software will cause major defects to be missed RISK 4 The user interface software for the sound systems will be delivered late into testing Refer to SCENARIO 2 - The IT Director for 'Safe as Houses' is recruiting a Programme Test Manager and has been provided with a skills matrix for four prospective candidates. The matrix shows the skill level (5 being highest. 1 lowest) for each candidate:

Consider which of these skills are key for a Programme Test manager in this scenario. Based on these, which candidate would be the most suitable?
SELECT ONE OPTION
正解:B
解答を投票する
You are monitoring the test results for the first week of system test execution to ensure they conform to the test plan objectives. You are guided by the list of test conditions and traceability matrix produced following test design. Test Plan objectives
* Approach - Risk-based and depth first
* Status reporting - Execution statuses must be either "Passed*, "Failed", "Blocked" or "Not Run"
* Traceability - Test execution results must be traceable back to the test conditions Test Conditions

Traceability matrix
Which one of the following is a correct statement regarding the current status of test plan objectives?
SELECT ONE OPTION
* Approach - Risk-based and depth first
* Status reporting - Execution statuses must be either "Passed*, "Failed", "Blocked" or "Not Run"
* Traceability - Test execution results must be traceable back to the test conditions Test Conditions

Traceability matrix
Which one of the following is a correct statement regarding the current status of test plan objectives?
SELECT ONE OPTION
正解:D
解答を投票する
Test Analysts are doing test design for a change request to an insurance comparison system. The system provides car insurance quotations, using data input by the user.
The change request states:-
Drivers must be aged between 17 to 85 years inclusive to qualify for insurance comparison.
The following Test Conditions have been identified:
1 Driver's age is less than the minimum
2. Driver's age is within the valid range
3. Driver's age is more than the maximum
The Test Strategy states the test techniques to be used include Equivalence Partitioning and Boundary Value Analysis. Using the Test Conditions and techniques stated in the Test Strategy, the following Test Cases have been created.

As the Test Manager you are reviewing these Test Cases for traceability to the Test Conditions and to ensure that the change request will be adequately tested in accordance with the Test Strategy.
Which of the following statements is FALSE? SELECT ONE OPTION
The change request states:-
Drivers must be aged between 17 to 85 years inclusive to qualify for insurance comparison.
The following Test Conditions have been identified:
1 Driver's age is less than the minimum
2. Driver's age is within the valid range
3. Driver's age is more than the maximum
The Test Strategy states the test techniques to be used include Equivalence Partitioning and Boundary Value Analysis. Using the Test Conditions and techniques stated in the Test Strategy, the following Test Cases have been created.

As the Test Manager you are reviewing these Test Cases for traceability to the Test Conditions and to ensure that the change request will be adequately tested in accordance with the Test Strategy.
Which of the following statements is FALSE? SELECT ONE OPTION
正解:C
解答を投票する
Which three of the following would be considered a good mix of technical and interpersonal skills (hard and soft), for a test team leader?
a. Ability to compliment a developer.
b. Presenting information regarding a test project progress to stakeholders c. Using a configuration management tool.
d. Ability to read a development coding language
e. Assessing a failure and documenting it correctly.
a. Ability to compliment a developer.
b. Presenting information regarding a test project progress to stakeholders c. Using a configuration management tool.
d. Ability to read a development coding language
e. Assessing a failure and documenting it correctly.