The Sen/ice Center at Universal Containers (UC) uses Service Cloud and Experience Cloud to manage its customer case lifecycle. UC wants to limit the number of interactions a customer has during the lifecycle. The project leader has asked the business analyst (BA) to visually illustrate the lifecycle.
Which document should the BA create?
Which document should the BA create?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Cloud Kicks is creating a new lead conversion process in Sales Cloud. During a recent sprint, the business analyst created user stories related to the Opportunity object. Test scripts were created for the lead conversion process. All of the test scripts passed and the new functionality was deployed. After deployment, end users reported error messages when manually creating new Opportunities.
Which area of user acceptance testing (UAT) was overlooked''
Which area of user acceptance testing (UAT) was overlooked''
正解:C
解答を投票する
Cloud Kicks (CK) wants the business analyst (BA) assigned to its Salesforce transformation project to help it achieve organizational success.
The BA guides CK through a set of activities that provides tangible value and helps CK reflect on the nature of its business and the value it provides to customers.
Which strategy is the BA employing?
The BA guides CK through a set of activities that provides tangible value and helps CK reflect on the nature of its business and the value it provides to customers.
Which strategy is the BA employing?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The data science team at Universal Containers (UC) has been asked to analyze the sales team's data within Salesforce. Early in their research, the data science team discovered concerns about data quality. UC has brought in a business analyst (BA) to help address the concern.
What should the BA focus on doing first during the initial discovery phase?
What should the BA focus on doing first during the initial discovery phase?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
While working on a new Sales Cloud feature request for the sales team at Northern Trail Outfitters, the business analyst (BA) uncovers a workflow which could have an impact on the service team. The sales director assures the BA that the impact to service would be minimal.
Which step should the BA take next?
Which step should the BA take next?
正解:B
解答を投票する
The technical team at Cloud Kicks is trying to deliver one of its Salesforce customizations. The business analyst (BA) has been asked to put assignments, test plans, decisions, and milestones in writing and share this document with stakeholders so there is less potential for confusion.
Which tactical document should the BA use to capture features?
Which tactical document should the BA use to capture features?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The Salesforce delivery team at Cloud Kicks consistently has user stories that developers start but are unable to complete during each sprint. During the most recent retrospective, the development team expressed that they are running out of time to complete the stories. The team used the INVEST checklist to diagnose why these stories are incomplete at the end of the sprint.
Which checklist item is the most likely reason why the stories are incomplete at the close of the sprint?
Which checklist item is the most likely reason why the stories are incomplete at the close of the sprint?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Cloud Kicks leadership wants to use custom code for functionality that can easily be created declaratively in Sates Cloud. The business analyst (BA) has been asked to advise leadership on how these approaches impact their solution options.
What is one of the BA's strongest arguments for using configuration over code?
What is one of the BA's strongest arguments for using configuration over code?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many features were left in the project backlog. NTO's IT team is beginning a new phase of work on the Experience Site to build additional features requested by business stakeholders and wants to include the items that were left in the backlog in the first phase.
How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
正解:C