H13-629_V2.0 無料問題集「Huawei HCIE-Storage (Written) V2.0」
An Engineer installed a OceanStor 9000 for a customer (a total of 5 OceanStor 9000 C Node, front and rear endsare 10GE TOE networking, on-site installation TOE network card). Then connected the signal lines, power lines, and debugged the software. During the installation there were issues. Which of the following description of these issues are correct? (Multiplechoice.)
正解:B、D
解答を投票する
In a clustered environment, data is placed on the shared storage, and identities between peers are equal and have the same access to the data. It is required that the clusterware have a control mechanism for concurrent access to such peerpermissions. In Oracle RAC, you use the _____ mechanism to do multiple node-to-node collisions control of access.
正解:B
解答を投票する
In the OceanStor VIS6600T dual-redundant switch network environment, using OceanStor Toolkit inspection found that "multi-path state detection "does not pass the inspection report. It is found that there are two routes in the 4 paths of the VIS6600T device's 0 node to each LUN of the array. The path status is disabled.
According to the analysis, the switch port connected to port 0 of port A0 of node 0 on node 0 of the VIS6600T is visible on the optical switch. The received optical power is much lower than the rated power of the optical module.
What actions should be taken to fix this?
According to the analysis, the switch port connected to port 0 of port A0 of node 0 on node 0 of the VIS6600T is visible on the optical switch. The received optical power is much lower than the rated power of the optical module.
What actions should be taken to fix this?
正解:A
解答を投票する