What component of the project scope definition defines project exclusions?

In which of the following organizational structures does the project manager have full authority on a project?

All of the following are inputs to the quality process EXCEPT:

The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected:
Actual cost = $50,000
Plan cost = $45,000
Earned value = $40,000
What is the cost performance index?

When would resource leveling be applied to a schedule model?

Work authorization forms are needed in order to:

Stakeholder analysis identifies what information and relates it to the purpose of the project?

Which is not an example of formal communication?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following is an example of contract administration?

Which of the following is NOT a reason to measure variances from the baseline?

What quality control tool graphically represents how various elements of a system interrelate?

Which of the following is an example of a group creativity technique?

You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of scope definition. Which of the following could happen if you don't correct this?

解説: (JPNTest メンバーにのみ表示されます)
Which process documents the business needs of a project and the new product, service or other result that is intended to satisfy those requirements?

The strong matrix versus a weak matrix.

You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on?

解説: (JPNTest メンバーにのみ表示されます)
You are a project manager of Software Product Company. After hired a person you got to know that many of this person's ideas were developed by the competing company. Are you going to implement the same ideas?

解説: (JPNTest メンバーにのみ表示されます)
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus an ETC (estimate to complete) the remaining work. Which of the following is a valid formula for calculating EAC?

Which of the following is generally the MOST CORRECT use of a project network diagram?

What is the number of stakeholders, if the project has 28 potential communication channels?