A building manager benchmarks a building's energy performance in ENERGY STAR Portfolio Manager for the purposes of Energy and Atmosphere Prerequisite, Minimum Energy Performance. The use of the energy use intensity (EUI) tool in Portfolio Manager also satisfies which of the following steps performed under Energy and Atmosphere Prerequisite, Energy Efficiency Best Management Practices?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A LEED AP Operations and Maintenance project is at the end of the second month of the performance period when the team notices that the water meter readings for one of the two submeters is not being recorded. What advice should the LEED AP give the project team in order to comply with Water Efficiency Credit, Water Metering?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)