MB-335 無料問題集「Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert」

You are a process engineer evaluating lean vs. Discrete processing. You warn to convert a Kanban item. This item has the following Lean setup:
* The setup uses a lean schedule group with a throughput ratio = 2.
* The process activity tied to production flow has the following runtime activity times: time = 3 mm. per quantity = 1.
* The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day).
* The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item s production flow activity.
What should you do?

You are a production manager at a company which produces large batches of coffee and creamers.
After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.
You need to add 20 grams of sugar and stir the product for an additional 0.S hours.
What three actions are required on the rework order? Each correct answer presents pan of the solution.
NOTE: Each correct selection is worth one point.

正解:A、B、D 解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
You need to determine the batch values on the combined mix batches for OperatorA.
Which values should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Explanation:
A manufacturer sends wiring harnesses to a vendor to be soldered to a connector. You create the subcontracting process in the bill of materials (BOM) and route to account for the items sent to the vendor.
You need to set up a new item model group for the service item.
Which three actions should you perform? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:

Explanation:
You need to set up the correct production solution for the assembly area. Which solution should you implement?

You need to configure the controller's ModelB asset requirements for the off-season.
What should you do?

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen A client subcontracts production work to a vendor for production operations.
You need to model subcontracting of route operations in production orders.
Solution: Ensure that the material routing process is independent of the services procurement process.
Does the solution meet the goal?

You are the quality assurance manager of a pharmaceuticals company.
One of your customers has requested to only receive batches of item B0001 that have an acid concentration between 5.5 - 10.5 percent.
You need to set up the customer specific batch attribute to track percent acid for B0001.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:

Explanation:
A manufacturing company uses discreet manufacturing to make skateboards. Production order picking lists are manually posted after finished good are reported as finished.
A production order has six picking lists posted. The quantities on the picking lists do not match any of the reported or finished quantities. This causes an inventory error for the raw materials. All taw material transactions must be tracked on production order and reconciled.
You need to process a single picking list for each production order.
What should you do first?

A company plans to account for indirect costs related to materials used to manufacture products.
The items used to manufacture products have surcharge rates that depend on the type of product being used.
You need to set up the costing sheet to include surcharges for specific items.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:

Explanation: