You need to modify the production order defaults for the manufacturing execution production order Start process.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Explanation:
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?

You need to configure system attributes.
Which attribute types should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Explanation:
A company produces multiple products that require an installation kit that includes 50 components.
The company does not want to include these 50 components in every Bill of materials (BOM). You have a BOW kit that includes all SO components, but you do not want it to produce a separate production order.
You need to set up the product BOM for the finished good.
What should you do?

A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling in a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point.

正解:A、B、D 解答を投票する
A co uses the asset management module in Supply Cham Management. The company has four conveyer systems in the warehouse. A robotic crane moves pallets of products to its conveyer int. Each robotic crane and conveyer line is considered a multilevel asset.
A work order arrives for a conveyer system. A technician completing the work observes that the robotic crane needs a repair. The technician is not qualified to work on the robotic crane.
You need to ensure that the robotic is repaired.
Which two options should you configure? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

正解:A、E 解答を投票する
A manufacturer uses Dynamics 365 Supply Chain Management to build bicycles.
When manufacturing releases production orders to the warehouse, the warehouse must avoid automatically releasing the bill of materials (BOM) and formula lines. The BOM and formula lines must be manually released later through a batch process.
You need to configure the functionality for the records.
At which two locations should you configure this functionality? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

正解:A、C 解答を投票する
A manufacturing company uses Dynamics 365 Supply Cham Management.
The company identifies a bill of materials (BOM) item that needs to be recalled for a product The engineering department needs to link customer support incidents and knowledgebase articles related to the product change.
Other items affected by this change must reference the same support incidents and knowledgebase articles.
You need to recommend features to facilitate this business process.
Which features should you recommend? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Explanation:
A manufacturing company uses time and attendance in Dynamics 365 Supply Chain Management.
Break times are paid. The cost of a break time must be charged at the pay rate of the job in progress when the break starts.
You need to configure the break times to charge against the job in progress.
Which two actions should you perform? Each answer presents a partial solution.
NOTE; Each correct selection is worth one point.

正解:B、D 解答を投票する
A company produces homeopathic lotions (or pain relief and uses Dynamics 365 Supply Chain Management.
Several components used in the production of the pain-relieving lotion and oils have special government- mandated reporting requirements.
You need to ensure the company can provide the appropriate reporting and tracking for these components.
Which parameters should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:

Explanation: