A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
正解:C
解答を投票する
A project has a BAC of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
正解:B
解答を投票する
A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?
正解:A
解答を投票する
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
Project title description
Preassigned resources
Budget
WBS
Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
Project title description
Preassigned resources
Budget
WBS
Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
正解:B