PK0-005 無料問題集「CompTIA Project+ Certification」

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

解説: (JPNTest メンバーにのみ表示されます)
A critical business initiative introduced new processes and technology to the organization. Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

解説: (JPNTest メンバーにのみ表示されます)
A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?

解説: (JPNTest メンバーにのみ表示されます)
A risk management team for a software project decided to outsource the development of a specific portion of a system due to a lack of internal resources. Which of the following risk responses does this demonstrate?

解説: (JPNTest メンバーにのみ表示されます)
For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is beginning a new project that will include a high number of complex deliverables. Which of the following is the best to use to track deliverables that are yet to be completed?

解説: (JPNTest メンバーにのみ表示されます)
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following is a quantitative key performance indicator?

解説: (JPNTest メンバーにのみ表示されます)
A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

解説: (JPNTest メンバーにのみ表示されます)
Which of the following is a typical characteristic of Scrum?

解説: (JPNTest メンバーにのみ表示されます)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡