PMI-ACP 無料問題集「PMI Agile Certified Practitioner」
A development team is calculating the number of story points they have completed at the end of an iteration.
Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.
Should the team add the feature's story points to their burndown chart?
Although quality assurance (QA) passed and successfully demonstrated one feature, it is not being included in the release package.
Should the team add the feature's story points to their burndown chart?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
How can a project team effectively work toward a common goal and communicate as they scale and expand to build a new business-critical platform, given that they have been responsible for a small customer-facing product with little complexity over the past 2 years?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An agile team has defined their definition of done (DoD) for a sprint. However, during the demo, the product owner is not sure if a user story can be marked as done.
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).
Select the most appropriate sequence of activities that would need to be completed to meet a well-defined, mature definition of done (DoD).
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
While reviewing the sprint burn down during a stand up. The scrum team identifies that they have fallen behind Upon further discussion they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck.
What should the scrum team do?
What should the scrum team do?
正解:B
解答を投票する
An agile team lead noticed their team's velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.
What should the agile team lead do at the end of this iteration?
What should the agile team lead do at the end of this iteration?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)