PMI-RMP 無料問題集「PMI Risk Management Professional」
A project team has completed the risk identification steps in a project and compiled a list of 25 risks. The team wants to create response plans for all the risks to avoid any future issues, but the resources and constraints limit the options.
What should the risk manager do?
What should the risk manager do?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
While implementing the risk response plan for a previously identified risk, some secondary risks were identified but not captured on the risk register. The project manager decided to review the risk management plan to ensure this does not happen for future, similar situations.
What should the project manager do next?
What should the project manager do next?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
What type of risk is this?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project is evaluating a new software to streamline the current purchase order process. The current process is labor-intensive and involves printing, ink signatures, scanning, and emailing. Several team members gathered cycle time data to gauge the current process and evaluate the new process.
What should the risk manager do next with the data set?
What should the risk manager do next with the data set?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).



How many total story points is the entire initiative?



How many total story points is the entire initiative?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well-defined. Which tool should the risk manager use to facilitate risk trigger identification in the upcoming risk review assessment?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
Where should the project manager find this information?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has finished the project charter for a project and has now moved into the planning phase.
In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.
What is the first resource the project manager should reference?
In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.
What is the first resource the project manager should reference?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The stakeholders of a building construction project are not comfortable with the project manager's handling of the project as they believe there is a financial risk. The project manager asks the risk manager to assist in demonstrating to the stakeholders that the project risks are under a tolerable threshold.
What should the risk manager do first to demonstrate this to the stakeholders?
What should the risk manager do first to demonstrate this to the stakeholders?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the project manager do next to determine risk impact of assumptions and constraints?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)