PMI-RMP 無料問題集「PMI Risk Management Professional」
A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.
How should the risk manager improve collaboration during risk planning?
How should the risk manager improve collaboration during risk planning?
正解:B
解答を投票する
A large, land-based infrastructure project has begun. The project makes assumptions about the site conditions and has economic, technical, and environmental constraints What should the project manager do next to determine risk impact of assumptions and constraints?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
While executing an oil extraction project in an environmentally sensitive area, weather is the main cause of delay in the project work. The risk manager was aware that the delays caused by the weather could not be avoided or mitigated.
What should the risk manager do to manage this risk?
What should the risk manager do to manage this risk?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The project manager is reviewing the lessons learned from a previous similar project. The previous project was delayed due to the delay in delivery of a gas turbine generator (GTG). Construction of the previous project had to be shut down unexpectedly to wait for the late delivery of the GTG.
What should the project manager do first?
What should the project manager do first?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)