PMI-RMP 無料問題集「PMI Risk Management Professional」

While planning for project execution phase stakeholders are making decisions on how to respond to known and new risks. What artifact should the stakeholders prepare?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?

解説: (JPNTest メンバーにのみ表示されます)
A risk manager of a complex project has identified a risk and believes a deeper understanding of the source and likelihood is necessary. How should the risk manager proceed?

解説: (JPNTest メンバーにのみ表示されます)
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?

解説: (JPNTest メンバーにのみ表示されます)
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?

解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?

解説: (JPNTest メンバーにのみ表示されます)
A project is at the final development stage. The test lead informs the risk manager that a key feature may not be testable due to changes in the environment What should the risk manager do?

解説: (JPNTest メンバーにのみ表示されます)
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?

解説: (JPNTest メンバーにのみ表示されます)
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?

解説: (JPNTest メンバーにのみ表示されます)
An organization faces immense competition in the market and decides 10 accelerate a key project. What is the first action for the project risk manager to take?

解説: (JPNTest メンバーにのみ表示されます)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡