A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
What should the risk manager do first?
What should the risk manager do first?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a construction project. Based on past experience, the project manager identifies a risk that a supplier of a critical material may not deliver on time. The project manager has already accounted for this risk in the risk management plan. If this risk materializes, the project manager plans to procure the material from a different supplier. A potential risk in this plan is that there may be differences in the material provided by the first and second supplier.
What type of risk is this?
What type of risk is this?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project team's manager is responsible for delivering a specific initiative for the organization. They are preparing for a monthly meeting where the manager will present on the current state of this initiative. The agile project lead sends the manager the following email with the current initiative status (Refer to the email exhibit).



How many total story points is the entire initiative?



How many total story points is the entire initiative?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?
What should the risk management professional do next?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager realizes the team undertaking the project work has fallen behind the planned schedule. The risk manager identifies a new risk resulting from this delay and will need to understand how this will affect the project deadline.
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
Which kind of numerical analysis should be performed to understand the worst-case scenarios?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A risk manager is preparing for the first meeting with their project sponsor on a potential project for a large client. The risk manager reviews their newly developed project risk register to identify any risks that should be analyzed further and begins by prioritizing the probability column based on the following criteria:
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
1 = Very Low
2 = Low
3 = Medium
4 = High
5 = Very High
What type of risk analysis is the risk manager performing?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A complex infrastructure construction project consisting of various stakeholders with diverse attitudes and opinions is in the execution phase. The project sponsor instructed the risk manager to evaluate the project environment and identify potential risks because many conflicts have arisen.
What should the risk manager do first?
What should the risk manager do first?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
What two actions should the risk manager do next? (Choose two.)
正解:A、B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
正解:A、C、D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
What is the expected outcome of developing the risk management plan?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
What is an effect of adding the correlation to the model?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A home solar panel project has many internal and external stakeholders including households, businesses, community groups, electric utility companies, local government officials, landlords, and investors. What should the project manager do when engaging stakeholders?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is trying to realize benefits from new material on an adaptive project. This is the first time the project team is using the material so the team does not have information to identify and analyze risks. A team member informs the project manager that a local university has recently published a research journal on the same material.
Where should the project manager find this information?
Where should the project manager find this information?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)