PMI-RMP 無料問題集「PMI Risk Management Professional」
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
What should the project manager have done to avoid this?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has been assigned to a project that is just starting. The organization has a very low risk appetite towards this project due to constraints on budget and schedule. The project stakeholders are very engaged on the project and want to ensure that there is clear visibility on the project risks and progress.
How should the project manager handle stakeholder expectations?
How should the project manager handle stakeholder expectations?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
What is the expected outcome of developing the risk management plan?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a complex construction project. During the risk identification process, hundreds of risks were identified. The team seems to be confused regarding on which risks to focus. The project manager advises the team to go ahead and start assessing the likelihood and impact of each risk.
What process is this part of?
What process is this part of?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project's design has been completed and approved on time. The construction subcontractor should be mobilizing to start construction but does not have the necessary materials in place, causing a delaying in the project. The risk register only contains risks for the design phase of the project.
What should the project manager have done differently?
What should the project manager have done differently?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)