PMP 無料問題集「PMI Project Management Professional (2024 Version)」
A project using a hybrid approach to migrate from a current system to a new and enhanced system is underway. The plan is to migrate the system in stages. However, the operations team is complaining that they are not ready to start supporting the new system.
How should the project manager effectively approach this situation?
How should the project manager effectively approach this situation?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water What caused this situation to occur?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
In the past, the project manager and the project team performed well using predictive methodology. However, the organization recently decided to adopt agile approaches, and the project sponsor wants to use an agile approach in an upcoming project.
Before initiating the project, what should the project manager do?
Before initiating the project, what should the project manager do?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project.
The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
What should the project manager do?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has team members around the world in many different time zones Project work frequently stalls because people in one office need to wait until another office is awake to have questions answered.
What should the project manager have done to avoid this?
What should the project manager have done to avoid this?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix What should the project manager do with regard to community engagement in this situation''
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)