PMP 無料問題集「PMI Project Management Professional (2024 Version)」

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?

A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document and include it in the lessons learned register.
What should the project manager do?

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond?

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds.
What should the project manager do?

A leader from project B consistently reaches out to a team member in project A for assistance.
What should project A's project manager do?

As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?

A project manager is reviewing the requirements of a large program.
Which requirements should the project team prioritize to avoid getting fines?

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.
What should the project manager do next?

A project manager and protect team are developing a strategic approach to engage the internal and external stakeholders.
Which approach should be followed?

解説: (JPNTest メンバーにのみ表示されます)
A network transformation project to increase efficiency and return on investment (ROI) is in the implementation stage. A conflict between the head of the network and the transformation manager arises.
What should the project manager do to manage this?

解説: (JPNTest メンバーにのみ表示されます)
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?

Drag and Drop Question
Match the project situation on the left to the meeting on the right where the situation could occur.
正解:
A project is on its second iteration out of eight. After some daily meetings, the project manager notices that one team member is always directing the meeting. The team is not comfortable with the situation and, as a result, the activities are blocked.
What should the project manager do?

A project manager is leading an innovation project that is facing a lot of risks due to a high level of uncertainty. What strategy should the project manager use to manage these risks using an agile approach?

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡