PMP 無料問題集「PMI Project Management Professional (2024 Version)」
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?
What should the project manager do?
正解:B
解答を投票する
A project manager is assigned to an automotive product development project in the middle of the pilot phase. According to the test lab, a durability test was completed with good results six weeks ago, but there were no reports left behind by the test engineer who left the organization the previous month.
What should the previous project manager have done to prevent this issue?
What should the previous project manager have done to prevent this issue?
正解:C
解答を投票する
A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?
What should the project manager do?
正解:D
解答を投票する
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?
What should the project manager do next?
正解:C
解答を投票する
A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.
What should the project manager do?
What should the project manager do?
正解:A
解答を投票する
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over
3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
正解:D
解答を投票する
A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
正解:B
解答を投票する
Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.
Which three actions should the project manager do? (Choose three.)
Which three actions should the project manager do? (Choose three.)
正解:A、B、D
解答を投票する
A project manager is assigned to a multiyear enterprise resource planning (ERP) solution project.
During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
During planning, the business sponsor emphasizes the importance of demonstrating value along the way, while maintaining the integrity of the final product.
How should the project manager establish the delivery model for this project?
正解:A
解答を投票する