A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two)
What two things should the project manager do? (Choose two)
正解:C、E
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix What should the project manager do with regard to community engagement in this situation''
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project The group uses a three-point estimating technique The project manager submits the estimated budget to the project sponsor for approval The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations What should the project manager do?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.
What should the project manager do?
What should the project manager do?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?
What should the project manager do?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An organization has recently decided to switch from a predictive to an agile delivery approach. The one ongoing project will still be led by a project manager. The agile teams for that project have not produced any documentation.
What should the project manager of the ongoing project do?
What should the project manager of the ongoing project do?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An enthusiastic, newly hired vice-president has been assigned as the product owner for a digital transformation project. The project manager advises the product owner that some of the functional requirements are not aligned with the chief information technology officer's (CTO) strategy.
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
The product owner tells the project manager that the CTO is not part of the project and should not be engaged at this moment.
What should the project manager do?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.
What should the project manager do?
What should the project manager do?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
What should the project manager do to ensure that key stakeholders are available for this project?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A key team member has recently gone through some personal issues that has affected their performance. The project manager noticed that the team member's emotional situation has affected the rest of the team's performance.
How should the project manager handle this situation?
How should the project manager handle this situation?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks Drag each risk type on the left to its correct example on the right
正解:
Explanation:
The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?
What is the project manager's priority in this situation?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this project?
What should the project manager do to ensure that key stakeholders are available for this project?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The rollout of a new finance system is in the execution phase. A number of issues have surfaced in the last month that are slowing the project down A new project sponsor has recently started with the company but has not had time to meet the project manager The project is at the point where the issues are significantly impacting delivery of the project How should the project manager alert the new project sponsor about these concerns?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)