PMP 無料問題集「PMI Project Management Professional (2024 Version)」
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
What should the new project manager do?
正解:A
解答を投票する
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
What should the project manager do to continue with the delivery plan and return to the expected velocity?
正解:A
解答を投票する
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds.
What should the project manager do?
What should the project manager do?
正解:C
解答を投票する
Drag and Drop Question
Match the project situation on the left to the meeting on the right where the situation could occur.

Match the project situation on the left to the meeting on the right where the situation could occur.

正解:

A project is on its second iteration out of eight. After some daily meetings, the project manager notices that one team member is always directing the meeting. The team is not comfortable with the situation and, as a result, the activities are blocked.
What should the project manager do?
What should the project manager do?
正解:D
解答を投票する