The program manager compiles a program performance report for review by the program governance board.
The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized After further analysis of the performance indicators the program manager should do which of the following*?
The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized After further analysis of the performance indicators the program manager should do which of the following*?
正解:A
解答を投票する
Near the completion of a transformation program, the operations manager is concerned that their department failed lo be notified in advance of the new service being transitioned into operations. They claim that their department did not approve this service and is now unprepared and untrained to support the transformation.
What should the program manager have done first to prevent this?
What should the program manager have done first to prevent this?
正解:C
解答を投票する
AI the beginning of the second year of a five-year strategic cycle, the program management team attends a checkpoint session to review the state of the company's strategy During the previous year, the company needed to comply with new government regulations that impacted this strategy.
Based on this information, what should the program manager do?
Based on this information, what should the program manager do?
正解:B
解答を投票する
A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete The program manager can select a design-build option to optimize the construction schedule to 1 5 years However heavy demand for steel is causing price increases and delivery delays. II this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1 25 years What is the expected time of delivery?
正解:C
解答を投票する
An insurance company launches a program to consolidate the multiple systems used by its agents This program will benefit stakeholders by offering efficient policy administration processes, improved customer service and the ability to grow market share However, since the new program will also introduce new policies and pricing controls, some stakeholders are opposed to its implementation To obtain consensus among stakeholders, what should the program manager do?
正解:B
解答を投票する
After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?
What should the program manager do to address this risk with the program sponsor and governance board?
正解:D
解答を投票する
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
To whom should the change request be presented?
正解:A
解答を投票する
An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the nsk management plan created?
正解:D