SAFe-SASM 無料問題集「Scrum SAFe Advanced Scrum Master (SASM)」
A Scrum Master is asked to help an Agile Release Train that has struggled through multiple Pls. They just finished the second Iteration in the current PI and have nothing to show at the System Demo. The ART stakeholders are concerned. What should be done?
正解:B